Movement control

Movement joints are used to eliminate or control cracking within
the fabric. The joints are located in strategic positions and allow
slight, predetermined movement without subsequent cracking to the
masonry.
Spacing, design and location of movement joints depends
principally on the dimensions and shape of the wall in question,
detailing techniques and the complexity of the structure. The
joints should be located at junctions which may be vulnerable to
cracking.
The position of movement joints will be strongly influenced by
structural and architectural considerations but the following may
prove useful as an indication of where control joints may be
necessary.
Cracking is most likely to occur in long straight walls.
Blockwork walls of excessive length should be divided into a series
of rectangular panels with movement joints between each panel. The
effects of end restraint need to be assessed when deciding on the
panel length. This can add either 25% or 50% to the actual length
if one or two ends are fully restrained.
It is upon this total length that the empirical rules are then
applied. In the case of Fyfestone blocks, the maximum length
between movement joints is 9m. The length of each panel should not
normally be in excess of twice the height of the panel and areas of
blockwork above and below openings should be treated as individual
panels.
The data below is a general rule of thumb for
methods of controlling movement in blockwork panels.
| LENGTH TO HEIGHT RATIO OF PANEL (L:H) |
SPACING OF CONTROL JOINT (architectural
masonry) |
SPACING OF BED JOINT (reinforcement (mm)) |
| > 2:1 |
6-9m |
- |
| > 2.5:1 |
6-9m |
600/675 |
| > 3:1 |
6-9m |
400/450 |
| > 4:1 |
6-9m |
200/225 |
Movement joints should be provided where changes of height,
thickness and profile (either on plan or section) occur in the
wall, since these junctions are particularly vulnerable to
cracking.
Control joints will be required at the junctions of intersecting
walls and junctions with columns, and also where walls are
penetrated by major service pipes and ducts, or where large chases
are incorporated to accommodate services.
A number of factors should be considered by the
designer when using Fyfestone:
- providing control joints at suitable centres
- using bed-joint reinforcement
- protecting the blocks before and during construction
- specifying the correct mortar
Detailed information is covered within BS5628: Part 3:
Control joints are vertical separations built into a wall and
located where cracking may occur due to excessive stresses caused
mainly by drying shrinkage.
As a general guide, the joints should be at regular spacing up
to 9m in external and internal walls.
It should be noted that on south and east elevations, the effect
of the early morning sun on these faces can raise the temperature
very rapidly and cause greater movement to take place than
elsewhere in the structure. It is recommended that the above rules
be strictly adhered to unless further advice is taken.
Control joints may also be required at:
- changes in wall height and thickness.
- junctions with other forms of construction e.g. steel
stanchions and reinforced concrete columns
- intersections with other walls and partitions – particular
attention should be given where return walls occur.
- return angles in L-, T- and U shaped buildings.
- chases or recesses for piping, pilasters, fixtures, etc.
movement joints in roof and floor slabs. These joints in the
main structure must be continued through the wall construction. The
width of the wall joint and the compressible filler should be
similar to that used in the roof and floor slabs. one or both sides
of some large wall openings, e.g. windows, louvres or doors.
However, the addition of localised bed joint reinforcement above
and below openings can often eliminate the need for control
joints.
FORMATION OF CONTROL JOINTS









The wall is built in the ‘normal’ half bond manner with the
exception that on alternate courses, half-length blocks are used to
form a straight vertical joint.
The sealant should be one of the following or
similar:
- an acrylic based sealant
- two-part polysulphide
- a silicone-based sealant
Internally, the joint should be left open as long as possible to
enable the wall to dry out thoroughly. Control joints should be
carried through all finishes. In cavity walls, the control joints
in each leaf should be offset. The flexibility of the cavity ties
is normally sufficient to compensate for the very small
differential movement between two leaves. Generally, the joint
spacing is greater on the inner leaf so the staggering of joints is
relatively simple.
HORIZONTAL CONTROL JOINTS
Limitation on uninterrupted height when the method of limiting
the uninterrupted height is adopted in accordance with BS 5628 :
Part 1, the outer leaf should be supported at intervals of not more
than every third storey or every 9m, whichever is less. This method
employs shelf angles and vertical joints, which subsequently
provides a means of vertical movement control. However, for
buildings not exceeding four storeys or 12m in height, whichever is
less; the outer leaf may be uninterrupted for its full height.
MOVEMENTS DUE TO THERMAL EFFECTS
In general, movements due to normal changes in temperature of
internal walls are likely to be small and not an important cause of
cracking. However, in long walls or partitions where variations in
temperature are likely to be large, care should be taken to
accommodate movement.
MOISTURE MOVEMENT
All concrete units shrink slightly after manufacture but part of
this shrinkage is reversible due to dry units expanding slightly
when wetted. However, care should be taken to ensure that all units
comply with the relevant European Standard for drying shrinkage
requirements. To minimise moisture movement, all masonry units
should be kept as dry as possible prior to laying and when laying,
they should not be soaked in order to adjust the suction for the
mortar.
DIFFERENTIAL MOVEMENT
If practical, products with different characteristics should not
be rigidly bonded together. Thus clay and concrete units should not
be mixed unless consideration has been made into allowing
independent movement.
All concrete products shrink slightly over a period of time, the
initial shrinkage taking place during the first six months to a
year. Likewise some clay bricks built on top of concrete brick
plinth walls may cause severe cracking in the plinth wall. Where
dissimilar materials are used, for example in cavity walls, it is
good practice to avoid the use of rigid ties and permanent bonding
together of brick or block work with the opposing component.
PRECAUTIONS
Procedures to minimise cracking:
- Use the correct grade of mortar: an unnecessarily strong grade
of mortar will concentrate the effects of any differential movement
on few and wider cracks. A weaker mortar will accommodate small
movements so that any cracking will be distributed as hair cracks
in the joints where they are less noticeable
- Bonding: cracking of masonry is more likely to occur if bond
patterns are not maintained and alignment of vertical joints
results. This can be exacerbated by poor workmanship
- Use masonry of low potential shrinkage. Ensure that the units
are dry before use and during laying
- Reinforce the masonry with joint reinforcement at locations of
high stress
- Allow for thermal and shrinkage stress by the correct
incorporation of control joints at appropriate intervals
Joint design should comprise a sealant cover either side of the
joint with compressible joint backing. The choice of sealant is
important. Fyfestone recommend the use of sophisticated sealant
such as two-part polysulphides or acrylic resin polymers. The
former is the most proven performer.
The need for periodic maintenance of joints should be recognised
and considered when positioning joints.
LOCATION OF MOVEMENT JOINTS
Movement joints in masonry may either be expansive or
contraction joints; the latter being free to accommodate any
tensile stresses. The incorporation of movement joints within a
wall structure should be in accordance with
BS 5628 : Part 3: 2005.
Movement joints should be installed at not greater than 9m
centres and may be formed as a straight butt joint. Or in a toothed
fashion in the coursework using a separate medium, such as dpc
material, and subsequently pointed in a suitably coloured mastic.
Flexible damp proof courses may also be used to act as a slip
planes between materials of different properties.
Care should be taken to ensure that all movement joints also
comply with the requirements of the other functions of the wall,
ie. lateral restraint, fire resistances, etc.
In estimating the correct spacing of movement joints, it is best
to design walls of concrete units into a series of panels. Areas
above and below windows and doors should be treated as individual
panels except where it is permissible to control cracking by the
use of bed reinforcement.
Generally the shape of the panels is critical in deciding the
susceptibility to cracking. It is more likely to occur if the
length exceeds about 1.5 to 2 times its height.
Care should be taken that there is no excessive end restraint
and if lateral stability is likely to be affected then dowels, one
end of which is not fixed, should be used to provide stability.
WALL TIES
Wall ties should conform to BS EN 845-1. For guidance on
selection and use of wall ties see BS 5628 : Part 3 : 2005.
TYPE OF MOVEMENT JOINTS
Examples of where movement control joints could
be located
- Expansion Joint
- Contraction Joint - Internal
- Contraction Joint - Internal and External
- At large chases or recesses
- At change of wall height
- Where wall is penetrated by large duct or services
- At change of wall thickness
- Expansion joint in floor slab
- At junction of columns, etc.
- Junction of steel frame
- Joint hidden by downwater pipe
- At staggered joints in a cavity wall
CONTROL OF CRACKING USING REINFORCEMENT
If it is impractical to divide walls into a large number of
panels because of, for example, a large number of openings, then
reinforcement can be introduced to distribute the areas of high
stress. It is still important to maintain panel length/height ratio
at 2-2.5. The reinforcement should be long enough, or have enough
overlap, to distribute stresses adequately and be provided with the
correct cover. All bed joint reinforcement must be used in
accordance with the manufacturers’ recommendations.
At window opening