Site Safety and Handling

Collar jointing is laying units back to back in normal aspect
with a 10–15mm mortar joint between the adjoining faces of the
units. The two leaves may be tied together. If tied either normal
ties or bed joint reinforcement may be used. Collar jointed walls
are not suitable for separating walls in dwellings.
To reduce the risk of injury, the project design, site
conditions and the way in which the work is organised should be
properly planned. Practical advice on these matters should help
designers, specifiers and those managing work on site as well as
those handling the blocks.
Handling Building Blocks
This guidance by the Construction Industry Advisory Committee
(CONIAC) covers the safe handling of architectural masonry, by
which the committee means all masonry units and blocks, including
those made of clay, concrete, reconstituted stone or any similar
man-made or natural material.
Handling of heavy building blocks can give rise to a wide range
of injuries, including serious injuries where the damage is gradual
and progressive over a substantial period of time.
Risk Assessment
1. To minimise the risk of injury:
- All hazards involved need to be identified
- The significant risks estimated; and
- Suitable precautions to avoid or reduce these risks
incorporated into safe systems of work
2. The main hazards are:
- Heavy loads and poor posture: excessive stress and strain
causing injury to muscles and tendons, particularly where handling
involves bending, twisting or other difficult postures;
- Slips, trips and falls: including damage caused by dropped
blocks;
- Sharp edges: cuts and abrasions to the skin;
- Skin hazards: dermatitis, burns and similar conditions caused
by contact with mortar (see HSE construction information sheet No.
26 Cement).
3. With block handling, the risk
of injury is largely determined by the weight of the block – the
heavier the block, the higher the risk of injury.
4.After taking account of expert
opinion and the long history of complaints over handling heavy
blocks, CONIAC has concluded that there is a high risk of injury in
the single-handed, repetitive manual handling of blocks heavier
than 20 kg (44 lbs).
5.If a single person handling is
needed, either blocks of 20 kg or lighter should be specified and
used or other precautions should be taken to reduce the risk by,
for example, the provision of mechanical handling. This would
contribute to the risk assessment required under the Manual
Handling Operations Regulations 1992.
6.With blocks weighing less than
20 kg. Manual handling risks are still significant and suitable
precautions should be taken to minimise these risks as much as
possible.
Precautions
Designers and specifiers should take the weight guideline into
account at the design and specification stage of the project. Where
it is not reasonably practicable to avoid specifying blocks heavier
than 20 kg, provision should be made for mechanical handling or for
laying by two people.
Project planners and contractors should follow the weight
guideline and ensure that the precautions listed below are taken
into account when planning the work and when devising safe systems
of work. Contractors should also give instruction and exercise
supervision to ensure that workers follow these plans and systems
of work.
The Task
Handle and lay building blocks in accordance
with the following:
- Plan to stack blocks close to where they will be used.
- Stack on a level, firm base and wherever possible without
double stacking of block packs
- Keep man-handling of blocks to a minimum and use mechanical
lifting and handling aids as much as possible, such as cranes,
fork-lift trucks with pallets, trolleys and telescopic
handlers.
Note: Ensure that the landing area of
scaffolding is adequate for the temporary loading of blocks.
- Always use mechanical lifting and handling or operate a
two-person system for blocks weighting more than 20 kg
- Arrange work to avoid over-reaching or twisting when handling
blocks
- Ensure good grip and secure foot placement in the working area
when handling blocks
Arrange the work so that blocks only need to be handled up to
shoulder height. Go higher by using staging, for instance. (Note:
further protection against falls may be necessary if the effective
height of guard rails is reduced). Particular care and attention is
needed for higher risk block laying such as when head room is
restricted, under soffits or below working platform level.
The working environment
Prepare roads and hard standing first and before blocks are on
site. In areas where blocks are carried or handled, keep the site
clear of obstacles or tripping hazards, such as discarded block
wrappings or stack ties. Uneven, slippery or unstable ground
conditions increase the risk of injury. Blocks should be protected
from the weather to avoid them getting wet and increasing in
weight.
Training
Workers should be given information and training on the systems
of work and procedures to be used on that site to ensure safe
manual handling of blocks. Suitable training will also be necessary
for designers, specifiers and those managing contracts.
Personal Protective Equipment
When handling blocks the normal protective equipment needed for
use on building sites should be provided by employers and worn by
individual workers; in particular, safety helmets, safety footwear
with protective toe caps and suitable gloves.
Wall Ties
Serious injuries have occurred when building double skin walls
due to contact with the sharp ends and edges of some types of wall
ties. The exposed sharp edges should be covered or safer wall ties
used.
SAFE HANDLING AND USE OF CONCRETE BLOCKS
Consideration of the points listed below will contribute
significantly to working and manual handling.
- Minimise manual handling by delivering units as close to the
place of use as safety considerations permit
- Move units in packs and by mechanical means whenever
possible
- Load units out to above knee height
- Ensure that normal protective equipment appropriate to
construction sites is both provided and used
- Ensure that appropriate eye protection and dust suppression or
extraction measures are provided when mechanically cutting or
chasing units
Additional considerations include:
- Manual Handling Operations Regulations requires employers to
carry out a risk assessment on all manual handling tasks
- The Construction (Design & Management) Regulations places
duties in the form of a mandatory Health & Safety system, on
clients/designers/contractors.
In an attempt to provide practical guidance for meeting the
requirements of these two regulations the Health & Safety
Executive (HSE) has issued Construction Sheet 37 ‘Handling Building
Blocks’ which advises that:
- There is a risk of injury in the single-handed repetitive
manual handling of blocks heavier than 20kg
- Units of greater than 20kg should be handled mechanically or
using a two person team if they have to be handled
repetitively
NOTE: It has been industry guidance for several
years that two person teams should be used for handling heavy
units.
The HSE guidance does not prevent an individual handling
manually small numbers of units of greater than 20kg. In
particular, ancillary units such as quoins or reveals would fall
into this category and would not be expected to be handled by a two
person team.
The guidance given in Construction Sheet 37 is not mandatory,
but gives a method of meeting the requirements of the
regulations.
Units of greater than 20kg may be specified and used to meet
particular design requirements provided that appropriate handling
methods are used.
For users who, for design reasons, would otherwise select units
of greater than 20kg but would prefer not to, a number of options
exist. The appropriate choice from the options available will
depend on the unit or wall properties dictated by the
application.
Choices include:
- Using lighter solid units having sufficiently similar
properties
- Using cellular/hollow units instead of solid units (having
almost identical properties to solid units)
- Using alternative construction techniques such as:
- i) Laying units flat to form a 190 or 215mm width wall
(suitable for finishes such as plastering or drylining)
- ii) Collar joining* units to form a 190 or 215mm width wall
(particularly suited to facing applications).
Whenever making the choice of units it is essential to ensure
that the desired performance characteristics of the finished wall
are not compromised.
SITE WORK
Storage on site
- Pallets should be stored on flat, level ground at a safe
distance from other trades, they should not be stacked on top of
one another.
- Products should be unpacked immediately prior to using as they
can be damaged once the packaging materials are removed.
- Remember that masonry units can be easily damaged by transport
or mobile plant moving around the site area. Ensure the pallets are
stored at a safe distance from roadways, access and exits
points.
- It is important that opened pallets are covered to prevent the
ingress of water, dirt or dust.
Blocklaying
To maintain the natural appearance of the finished wall, it is
recommended that blocklayers should use blocks from several packs
whilst proceeding with construction.
During heavy rain blocklaying should be discontinued unless the
work is protected. Protect the top of the work against rain, snow
and frost when stopping work an hour or more and especially
overnight. The face of the work should also be protected against
splashes from the ground, scaffolding and other construction
activities.
- Masonry units should only be laid by suitably experienced
operatives
- Unprotected scaffolding poles, planks etc; should not be
supported by the cast stone units
- Brace constructions to prevent damage to freshly assembled
materials
- All units should be laid and adjusted to their final position
while the mortar is still plastic.
- Mortar exuding from joints should be cut away avoiding smearing
the face of the unit
- Installation should not be carried out during heavy rain unless
the work is protected. When work stops for more than an hour or
two, especially overnight, the top of the work should be protected
against rain, snow and frost. The face of the work should also be
protected against splashes from other construction activities
- Masonry construction should not be carried out in frosty or
freezing conditions, or if the temperature is at or below 3 ºC,
unless precautions are taken to ensure that the mortar has a
minimum temperature of 4 ºC when laid and is protected until this
has hardened. Precautions may also be required if the temperature
is 3 ºC when the mortar is laid but could subsequently fall below
freezing point before the mortar has hardened, e.g. overnight
- During construction it is advisable to protect finished work
using appropriate gauge polythene sheeting. This prevents mortar
drips, mastic, paint and other construction materials staining or
adhering to the masonry. Mortar, in particular, is very difficult
to remove
If the temperature is at or below 3ºC then blocklaying should
not be carried out unless precautions are taken to ensure that the
mortar has a minimum temperature of 4 ºC when laid and is protected
until it has hardened. Precaution may also be required if the
temperature is 3 ºC when the mortar is laid but could subsequently
fall below freezing point before the mortar has hardened (e.g.
overnight).
Chasing
A rotary chasing machine or mechanical disc cutter is
recommended where the use of hollow blocks is not possible and
chasing is necessary. Vertical chases should not exceed one third
of the wall/leaf thickness and horizontal chases should not exceed
one sixth of the wall/leaf thickness. In load-bearing walls the
effect of a reduced section area caused by chasing should be
checked. Chases should not impair the strength or stability of the
wall in any event.
Transporting the UnitsDuring transit the following points should
be considered:A suitable vehicle e.g. rigid or articulated trailer
preferably with air suspension should be used for transport.Units
should be covered during transit to protect them from saturation
and staining.Bearers should provide adequate support to prevent
incidents of point loading of the units.
Palletised deliveries of Architectural Masonry should be
unloaded either by grab or forklift, using suitable forks. Under no
circumstances should scaffold poles, timbers etc. be used to carry
or support the pallets.When using grabs, these should grip the
pallet, not the product.Slings should not be used unless previously
discussed with the manufacturer.Where slings are used to lift
individual units, the arrises of the unit should be protected and
the sling positioned to provide an even support.
Site HandlingThe safe handling of Architectural Masonry
components is essential in order to ensure that they remain
undamaged. Where handling information is not clear, contact the
supplier for further recommendations.A manual handling assessment
should be carried out before the units or pallets are moved.Where
units are supplied with lifting sockets or eyes these must be
used.
Avoid side loading to sockets by using a lifting beam where
necessary.Always use suitable plant for moving the product around
site and ensure wherever possible that units are delivered to the
work area before any obstructions are put in the way.Units should
be adequately supported to ensure ease of handling. Care must be
exercised not to drop the product. Re-use interior packing to
protect faces, arrises etc during site handling.Care should be
taken not to slide the units across each other.Don’t store pallets
on sloping or uneven ground. Make sure storage area is flat, level
and dry.
Never stack pallets and large units on top of each other.When
unpacking products, do not burst open the wrapping either by hand
or with site tools. It should be cut open with a knife, taking care
not to damage the faces.When moving pallets of Architectural
Masonry units, always re-use interior packing to prevent damage to
faces, arisses and profiles.
Site Storage
All Fyfestone architectural masonry is banded, shrink wrapped
and banded onto pallets.
Once the product is on site, the following guidelines should be
followed:Palletised products should be stored on flat, level, dry
ground at a safe distance from other trades, roadways, etc. to
prevent damage to the aesthetics and structure of the product.
Runners should be used to support pallets on soft ground.Never
stack pallets of products on top of one another.
Individual units should not be stacked face to face without
appropriate interface material (manufacturers packaging and
protective materials should be used for this).Individual units
should be suitably supported by timber or plastic bearers.Products
should remain packaged until immediately prior to use.When
unpacking the product, strapping/packaging should be carefully cut,
not ‘burst open’.
Ensure that care is taken when cutting the packaging so that the
face of the unit is not damaged by the knife blade.It is important
that opened packs of Architectural Masonry are covered with
polythene sheeting to prevent the ingress of water, dirt or
dust.
Protection
All blockwork should be protected from rain as much as possible.
At the end of each day blockwork should be covered, this is
particularly important in the case of hollow blocks to avoid
saturation. Prevention of excessive moisture will reduce the risk
of efflorescence or lime bloom, which is generally attributable to
a build up of moisture somewhere within the wall.
Consideration should also be given to propping high or long
walls where they are not properly restrained until completion of
the walls. This could also apply to internal walls, originally not
designed for wind loads, being constructed before the envelope of
the building is complete.
Good protection should be maintained throughout the construction
of the project, including the use of toe boards on scaffolding and
polythene sheeting to plinths and cills to prevent staining from
mortar splashes.
Sheeting should be left in place until completion and further
protection given to areas exposed to site traffic or following
trades.
Unless the work is protected when proceeding there is always the
risk that sudden Frosts or showers will cause damage.
NOTE: The appearance of finished masonry may be
affected by failure to protect the work during construction.
Cutting
The general tolerance on cut dimensions is +2, -2mm, although in
certain circumstances it is not possible to achieve this, e.g.
where a shallow cut is less than 25° to a face.
The general tolerance on cut angles is ±1.5° and taper-to-cut
faces will be within +1, -1mm.
Cutting Masonry on site
The range of specials Fyfestone produce to aid the construction
process significantly reduces the amount of cutting needed on site.
However, when faced with limiting situations, it is not always
possible to manufacture a unit to accommodate every situation and
therefore site cutting of units may be necessary. It is advisable
to cut blockwork on a clipper bench station with a Diamond-tip
blade and a fresh supply of lean, uncontaminated water.
The size and thickness of blade is also very important. For
instance if cutting a full block into two halves, a 10mm blade is
necessary to ensure that 2 x 215mm blocks are achieved, thus
eliminating any extra length by using a thinner blade, (i.e., a 4mm
blade will give 2 x 218mm units).
The cutting slurry produced is unavoidable and needs to be
washed away from the face of the units immediately after cutting.
The chemical reaction caused by cutting reactivates the cement,
which hardens onto the first material it, makes contact with after
cutting. The heat generated in the cutting process accelerates
this. Dry cutting is not recommended because of this reaction.